Central computer evaluation, February 14-28, 1955
Crane, J. D.; Thompson, S. L.
DownloadMC665_r15_M-3326.pdf (933.6Kb)
Date
1955-01-25Abstract
From 13 February to 28 February 1955, the performance of the central computer was monitored by studying log entries and by carrying out a series of tests on 28 February. Mean good-time and the per cent of assigned time that was unusable was determined by examining the log. Margins and trends in the margins were also determined. The test on 28 February consisted of shock tests and an eight-hour period during which various reliability programs were run.
Description
Includes: study of log entries; marginal checking data; central computer test run; power shut-down test; and computer test time schedule.