Group 62 Section Leaders Meeting -- December 14, 1953
Kromer, A. P.
DownloadMC665_r06_M-2574.pdf (1.103Mb)
Date
2009-05-09T05:07:54ZAbstract
SDV demodulator circuitry has been reviewed and accepted. Phone line transmission characteristics are being determined in conjunction with Bell Laboratories Project ADES personnel. Simplification of equipment to handle inputs having a relatively slow data rate is under study. Coordination of output system and equipment development is to be done by a joint IBM--Div. 6--Div 2 committee. Formalizing of the release for design completion and for construction of the two prototype systems is to be outlined in M-2575. Operational aspects of the display equipment for both Direction Center and Combat Center are being considered jointly by Lincoln, ADES and ADC.