SAGE system meeting, January 24, 1955
(Lincoln Laboratory - Division 6, 1955-01-27)Minutes of weekly SAGE System meeting discussing proposed change in procedure, charactron display, Mark X radar, exhibit AFCRC 17, direction center floor plan changes, Lincoln Laboratory visiting committee, test specifications ... -
Group organization list
(Lincoln Laboratory - Division 6, 1955-03-10)List of Division 6 staff by group. -
Minutes of the IBM-L/L SO concurrence meeting no.48 held at Lincoln Laboratory 15 December 1955
(Lincoln Laboratory - Division 6, 1955-12-16)Minutes of an IBM-SO concurrent meeting discussing specifications for utilizing the Kelvin and Hughes Rapid Processing Photographic Projection system in XD-1 command post; second floor layout of Building F; satellite ... -
Improved memory cores produced in Lincoln Laboratory
(Lincoln Laboratory - Division 6, 1955-04-13)Recent memory core production in the Lincoln Laboratory pilot plant has offered an improved variety of cores for experimental project use. Typical characteristics are shown for these cores and the principal advantages to ... -
IBM-SO concurrence meeting no. 28 held at Lincoln Laboratory 26 May 1955
(Lincoln Laboratory - Division 6, 1955-05-31)Minutes of an IBM-SO concurrent meeting discussing GFI monitor equipment for XD-1 and the production machine, auxiliary consoles specifications, card machine input-output duplex, tape power supply unit for AN/FSQ-7, auxiliary ... -
Rough notes on systems planning meeting on 7 February 1955 at 0930E
(Lincoln Laboratory - Division 6, 1955-02-07)Minutes of a systems planning meeting discussing initial specifications; status of auxiliary memory; plans and schedules; list of committee members; proposed format of M notes; and prime power. -
Changes and additions to laboratory personnel list
(Lincoln Laboratory - Division 6, 1955-07-20)List of changes and additions to Division 6 personnel at Lincoln Laboratory in July 1955. -
Geometry of magnetic memory elements
(Lincoln Laboratory - Division 6, 1956-01-18)Two possible memory element geometries — the thin film and the toroid — are considered. The calculations show that under certain conditions the thin film geometry may be preferable for use in a very high-speed memory. -
Remarks on domain patterns recently found in BiMn and SiFe alloys
(Lincoln Laboratory - Division 6, 1955-12-27)Memorandum discussing domain patterns in BiMn and SiFe alloys. -
Master reference list of equipment specifications for XD-1
(Lincoln Laboratory - Division 6, 1955-11-18)Supplement to the second master reference list issued by the Systems Office, which includes only concurred changes, revisions, and clarifications to XD-1 specifications. -
Master reference list of equipment specifications for XD-1
(Lincoln Laboratory - Division 6, 1958-10-09)Compilation of all the active technical specification documents which received Lincoln-IBM concurrence for AN/FSQ-7 (XD-1) design. The list is a revision of the previous list, 6M-3851-7, and was brought up to date as of 9 ... -
Results of the system tests (phases V and VI) on the AN/FSQ-7 (XD-1) during November 1955.
(Lincoln Laboratory - Division 6, 1955-01-11)Results of system tests performed on the LRI element and the crosstell element during the month of November 1955. -
SAGE system meeting, February 7, 1955
(Lincoln Laboratory - Division 6, 1955-02-07)Minutes of weekly SAGE System meeting discussing XD-1 etched cards, changes in D. C. building, status of J. A. O'Brien's space requirement document, status of specifications for display cables, IBM school in Building F, ... -
Report of committee studying failure reporting in the SAGE and experimental subsectors
(Lincoln Laboratory - Division 6, 1955-09-09)Recommendations of the committee studying failure reporting, appointed at a meeting on 14 June 1955. -
Central computer evaluation no.2, February 28 - March 14, 1955
(Lincoln Laboratory - Division 6, 1955-01-27)On 1 March 1955, a new memory element was to be added to the computer. The evaluation procedure was set to duplicate the procedure used from 14 February to 28 February 1955, except that the memory test programs used during ... -
XD-1 evaluation, 13 July 1955
(Lincoln Laboratory - Division 6, 1955-09-12)Second evaluation of the CD addressable drums performed on 13 July 1955. -
SAGE System meeting 9 May 1955
(Lincoln Laboratory - Division 6, 1955-05-09)Minutes of weekly SAGE System meeting discussing new report editor, report on recruiting program, committee on academic problems, trip to EADF, LRI monitors, SAGE test program, and meetings scheduled that week. -
SAGE System meeting 26 September 1955
(Lincoln Laboratory - Division 6, 1955-09-26)Minutes of weekly SAGE System meeting discussing Group 61 programmers, display tubes, RECI status, test planning manpower, and meetings scheduled that week. -
SAGE System meeting 2 May 1955
(Lincoln Laboratory - Division 6, 1955-05-02)Minutes of weekly SAGE System meeting discussing SAGE test committee, computer time allocation XD-1, auxiliary drums XD-1, large board display, 750 cps outputs, heat dissipation in AN/FSQ-7 equipment, distribution of ... -
Minutes of the IBM-L/L SO concurrence meeting no.44 held at Lincoln Laboratory 10 November 1955
(Lincoln Laboratory - Division 6, 1955-11-14)Minutes of an IBM-SO concurrent meeting discussing minutes of concurrence meeting no.40; changes to the LRI specifications; changes to the duplex maintenance console; changes to selection and input-output control ...