Project Whirlwind: Recent submissions
Now showing items 741-760 of 1737
-
T.I.R. release of operational specifications and XD-1 equipment specifications
(Lincoln Laboratory - Division 6, 1955-07-28)Technical Information Releases were used for equipment specifications and operational specifications for both the prototype and production machines. -
SAGE System meeting 27 June 1955
(Lincoln Laboratory - Division 6, 1955-06-27)Minutes of weekly SAGE System meeting discussing building redesign, card machines for XD-1, ADES monthly status meeting, console layouts for AN/FSQ-7, results of meeting with EADF, basic circuit and component approvals, ... -
Laboratory personnel
(Lincoln Laboratory - Division 6, 1955-12-01)List of Division 6 personnel at Lincoln Laboratory in December 1955. -
IBM-SO concurrence meeting no. 26 held at Lincoln Laboratory, 5 May 1955
(Lincoln Laboratory - Division 6, 1955-05-06)Minutes of an IBM-SO concurrent meeting discussing proposed specification for input pattern generators for XD-1 and XD-2, specification for the input pattern generator for the production machine, command post room in ... -
Laboratory personnel
(Lincoln Laboratory - Division 6, 1955-01-01)List of Division 6 personnel at Lincoln Laboratory in January 1955. -
SAGE system meeting, March 14, 1955
(Lincoln Laboratory - Division 6, 1955-03-14)Minutes of weekly SAGE System meeting discussing status of XD-1 schedules, Lincoln-IBM coordination committee, other meetings, ADES liason, and engineering-installation phasing committee summary report. -
Laboratory personnel
(Lincoln Laboratory - Division 6, 1955-08-01)List of Division 6 personnel at Lincoln Laboratory in August 1955. -
Minutes of IBM-Lincoln concurrence meeting no. 17
(Lincoln Laboratory - Division 6, 1955-03-08)Minutes of an IBM-Lincoln concurrence meeting discussing long-range radar input word layout, input channel switching, crosstelling inputs, and outputs. -
Minutes of the IBM-L/L SO concurrence meeting no.46 held at Lincoln Laboratory 2 December 1955
(Lincoln Laboratory - Division 6, 1955-12-05)Minutes of an IBM-SO concurrent meeting discussing prime power specifications; output MCD specifications; XD-1 equipment list; AXD write interlock; phosphor; spare parts policy; specifications for AN/FSQ-8 equipment; ... -
SAGE System meeting 10 October 1955
(Lincoln Laboratory - Division 6, 1955-10-10)Minutes of weekly SAGE System meeting discussing survey of Division 6 staff manpower requirements, Group 61 requirements, document distribution, Bendix meeting, ADES list of items requiring action, tape conversion equipment, ... -
Specifications for the central computer system for the AN/FSQ-7, supplement 4
(Lincoln Laboratory - Division 6, 1955-10-24)The AN/FSQ-7 specifications for the Central Computer System as recommended by Lincoln Laboratory were listed in 6M-3291 (released by T.I.R. #1-57), 6M-3291 Supplement 1 (released by T.I.R. #1-66), 6M-3291 Supplement 2 ... -
SAGE System meeting 19 December 1955
(Lincoln Laboratory - Division 6, 1955-12-19)Minutes of weekly SAGE System meeting discussing proposed IBM building, Group 61 space, systems maintenance programs, results of Air Force phasing meeting, Boeing-Lincoln study group progress, visit to ERA, and meetings ... -
Specifications for the central computer system for the AN/FSQ-7, supplement 5
(Lincoln Laboratory - Division 6, 1955-12-15)The AN/FSQ-7 specifications for the central computer system as recommended by Lincoln Laboratory are listed in 6M-3291, (released by TIR #1-57) and in 6M-3291, Supplements 1, 2, 3, and 4 (released by TIR's #1-66, 1-78, 1-93, ... -
Results of the system test (phase II) performed on the AN/FSQ-7 (XD-1) during July, August, and September 1955
(Lincoln Laboratory - Division 6, 1955-11-01)Results of a system test performed on the magnetic tapes and fifteen addressable drum fields. -
SAGE System meeting 25 July 1955
(Lincoln Laboratory - Division 6, 1955-07-25)Minutes of weekly SAGE System meeting discussing Group 63 space in Building A, justification for additional funds for XD-1, navy visitors, communications meeting in Colorado Springs, requirement for staff member for XD-1 ... -
Minutes of section leader's meeting, July 29, 1955
(Lincoln Laboratory - Division 6, 1955-08-09)Minutes of a section leader's meeting discussing 700 study, plans for duplex standby, equipment changes in FSQ-7, secretaries, S and EC Group - cooperation on utility programs, report on the dissection of SAGE test activity, ... -
Trip to NSA, Washington, D. C.
(Lincoln Laboratory - Division 6, 1955-03-30)NSA in Washington submitted to Philco a purchase description for a computer, SOLO, to be built with an SBT control and arithmetic unit and a 4O96 register ferrite core memory. NSA and Group 63 agreed to maintain close ... -
SAGE System meeting 24 October 1955
(Lincoln Laboratory - Division 6, 1955-10-24)Minutes of weekly SAGE System meeting discussing new meeting time, IBM reorganization, visitors to Building F, tape conversion equipment, release of operational specifications, recruiting for Rand, test equipment for SAGE, ... -
SAGE System meeting 18 April 1955
(Lincoln Laboratory - Division 6, 1955-04-18)Minutes of weekly SAGE System meeting discussing Taylor's trip to Willow Run Research Center, ADES monthly status meeting, communications between the First Direction Center and P-sites, lighting in Building "F," operational ... -
Minutes of the IBM-SO concurrence meeting no. 34 held at Lincoln Laboratory 21 July 1955
(Lincoln Laboratory - Division 6, 1955-07-22)Minutes of an IBM-SO concurrent meeting discussing XD-1 console equipment; console equipment and label layouts; government furnished equipment; test equipment for duplex central; PERSELBSN codes for production machine; ...