dc.contributor.author | Gray, Philip J. | en_US |
dc.date.accessioned | 2009-06-12T22:12:07Z | |
dc.date.available | 2009-06-12T22:12:07Z | |
dc.date.issued | 1954-06-08 | en_US |
dc.identifier | MC665_r13_M-2859 | en_US |
dc.identifier.uri | http://hdl.handle.net/1721.3/40316 | |
dc.description.abstract | The contract for construction of Building B started June 7th. A study group is being set up to investigate a smaller and faster computer for air defense at advanced locations. IBM is now back scheduled an average of six weeks on XD-1. | en_US |
dc.language.iso | en | en_US |
dc.publisher | Lincoln Laboratory - Division 6 | en_US |
dc.relation.ispartofseries | Project Whirlwind Memo M-2859 | en_US |
dc.relation.ispartofseries | Project Whirlwind Collection, MC665 | en_US |
dc.title | Group 62 Section Leaders Meeting - June 7, 1954 | en_US |
dc.type | Technical Report | en_US |