SAGE System meeting 29 August 1955
(Lincoln Laboratory - Division 6, 1955-08-29)
Minutes of weekly SAGE System meeting discussing liaison with cooperating agencies in experimental subsector, lighting in ready room, air conditioning in Building F, display meeting, tape conversion equipment, and meetings ...
SAGE System meeting 18 April 1955
(Lincoln Laboratory - Division 6, 1955-04-18)
Minutes of weekly SAGE System meeting discussing Taylor's trip to Willow Run Research Center, ADES monthly status meeting, communications between the First Direction Center and P-sites, lighting in Building "F," operational ...
SAGE System meeting 24 October 1955
(Lincoln Laboratory - Division 6, 1955-10-24)
Minutes of weekly SAGE System meeting discussing new meeting time, IBM reorganization, visitors to Building F, tape conversion equipment, release of operational specifications, recruiting for Rand, test equipment for SAGE, ...
SAGE System meeting 1 August 1955
(Lincoln Laboratory - Division 6, 1955-08-01)
Minutes of weekly SAGE System meeting discussing display system, study - 700 series IBM machines, card preparation room, schedules for operational and mathematical specifications, industrial management study, and meetings ...
Discussion of Lincoln concurrence on engineering-installation phasing committee, summary report #6
(Lincoln Laboratory - Division 6, 1955-03-22)
Lincoln Laboratory concurrence on the Engineering-Installation
Phasing Committee, Summary Report #6 was discussed at a meeting of interested Lincoln Laboratory personnel on 22 March 1955. It was agreed that Lincoln would ...
SAGE System meeting 9 May 1955
(Lincoln Laboratory - Division 6, 1955-05-09)
Minutes of weekly SAGE System meeting discussing new report editor, report on recruiting program, committee on academic problems, trip to EADF, LRI monitors, SAGE test program, and meetings scheduled that week.
SAGE System meeting 20 June 1955
(Lincoln Laboratory - Division 6, 1955-06-20)
Minutes of weekly SAGE System meeting discussing IBM coordination meeting, acceptance tests, aircraft requirements in the experimental subsector, RETMA committee proposals, Bendix representation at Lincoln, and meeting ...